From the VP of operations:
All,
This notice is to inform you of upcoming system outages that Facilities Management is planning in order to perform repairs to critical systems. I ask all recipients to forward this email to your Chairs, facility reps and staff. If there is an adverse impact please let me know promptly so we can discuss.
Campus Wide Power Outage:
Baltimore Gas and Electric has been working hard to complete repairs identified through a comprehensive inspection of their electrical distribution system. While many of the repairs are being made without the need for a campus wide outage, BG&E requires one campus wide outage to repair three deficiencies that were identified.
This outage is being scheduled for Friday 29 Nov 6am-4pm.
Chilled Water System Outage:
Maintenance work on our Chilled Water Loop is being scheduled for the week of 6-10 January 2020. The Chilled Water System would be turned off at 7am on 6 Jan and would be turned back on by 5pm 10 Jan.
During this 5 day outage, no process chilled water will be available.
There will be no noticeable difference to building temperatures during this outage.